The Stages of Building a House Extension: A London Timeline
What happens, in what order and for how long, from the first drawings to the completion certificate, with the London steps that general guides leave out.
In short: A London house extension runs in two halves. Before work starts: design and drawings, planning permission or a lawful development certificate (8 weeks from validation), party wall notices (one to two months), a Thames Water build-over agreement if you are near a public sewer, structural calculations and building regulations approval. Then the build: for a typical single-storey rear extension, about 14 to 16 weeks on site, from groundworks through the structure, roof, first fix, plastering, second fix and decoration, inspected by building control at the stages it specifies and ending with a completion certificate.
Before work starts
1. Survey, design and drawings
A measured survey of the house, then design drawings. Allow roughly 4 to 8 weeks for a single-storey extension and 6 to 10 weeks for a double-storey, in our experience. The design decides almost everything that follows: whether you need planning permission, whether you are near a sewer, and what the structural engineer has to design.
2. Planning permission or a lawful development certificate
If the extension needs planning permission, councils are expected to decide householder applications within 8 weeks of validation, the day the application is accepted as complete, not the day it is sent. If it is permitted development, a lawful development certificate proves it, also with an 8-week target. In the year to June 2026, 93% of householder decisions in England were made in time. Our planning permission guide covers which route you need.
3. Party wall notices
Under the Party Wall etc. Act 1996, work on a shared wall needs at least two months' notice, and building on the boundary line or excavating near a neighbour's foundations needs one month. Neighbours have 14 days to reply in writing; if they do not consent, a dispute is treated as having arisen and one agreed surveyor, or one each, prepares an award. A neighbour can agree in writing to an earlier start. Our party wall cost guide explains the costs.
4. Building over or near a sewer
If the extension will be within 3 metres of a public sewer or 1 metre of a public lateral drain, Thames Water must agree to it before you build. Simple cases can be quick; complex ones can take months, so check this early. Our build-over agreement guide explains the process.
5. Structural design and building regulations
A structural engineer designs the foundations, steels and any underpinning. Building regulations approval comes from the council or a private registered building control approver, by one of two routes: full plans, where the drawings are checked before work and a decision usually follows within five weeks, or a building notice, where work can start two days after notice is given but without formal approval of the drawings. On larger extensions we recommend full plans.
6. Contract, programme and the CDM regulations
A written contract sets the price, programme and payments; for a homeowner, the JCT Building Contract for a Home Owner or Occupier is one common form, and we build on JCT contracts. Under the Construction (Design and Management) Regulations 2015, a homeowner's client duties pass automatically to the contractor, or to the principal contractor where there is more than one, unless a designer agrees in writing to take them on.
The build, week by week
These are typical stages and weeks on site for a single-storey rear extension, from our own projects. Larger, double-storey and wrap-around extensions take longer.
| Weeks on site | Stage | What happens |
|---|---|---|
| Before week 1 | Set-up | Hoarding, welfare, protection to the house and garden, skip or grab lorry access, any pavement licences |
| 1–3 | Demolition and groundworks | Old structures removed, foundations dug and inspected, concrete poured, new drainage laid and tested |
| 3–7 | Structure and walls | Damp-proof course and floor slab, walls built, steel beams installed to the engineer's design |
| 6–9 | Roof and weathertight | Roof structure, insulation and covering, rooflights, windows and doors |
| 8–11 | First fix | Electrics, plumbing, heating and underfloor heating run before walls and floors are closed in |
| 10–14 | Plastering and second fix | Plaster and screed, then sockets, switches, radiators, sanitaryware and the kitchen |
| 13–16 | Finishing | Flooring, decoration, external making good, snagging walk-round and handover |
Plaster and screed must be dry before floors and decoration go on. Drying times depend on thickness, temperature and ventilation, so a moisture reading decides, not the calendar.
Breaking through into the house
Most families stay at home during an extension. The new part is built against the existing back wall, which is usually opened up near the end, once the extension is weathertight and the steel is in. The break-through itself typically takes one to three days, with temporary screens and dust control, and that is the most disruptive part of the job.
Building control inspections
Since 1 October 2023 the building regulations in England no longer list fixed inspection notices for each stage. Your building control body tells you which stages it will inspect and when it must be notified. Typical stages are the foundation excavation, the oversite and damp-proof course, drainage before it is covered, insulation and the structure before plastering, and completion. The statutory notices that remain include two days' notice before starting work and notice within five days of completion.
Completion certificate and electrical certificates
After the final inspection, building control issues a completion certificate, usually within eight weeks on the full plans route. Keep it: solicitors ask for it when you sell or remortgage, and missing paperwork can delay both. Electrical work is certified separately, by an electrician registered with a competent person scheme, who notifies building control for you. A completion certificate confirms the work met the regulations when inspected; it is not a guarantee of workmanship.
Paying for an extension
There is no legal cap on deposits. Which? advises a reasonable deposit, mainly where materials or bespoke items have to be ordered, payments tied to completed stages of work, and holding the final payment until you are satisfied. Stage payments against work done, with a small retention held for the defects period, is common practice, and a written contract should set this out before work starts.
Frequently Asked Questions
Can I start building before planning permission?
Only if the extension is permitted development. A lawful development certificate is the way to prove that before you start. Party wall notices and building regulations still apply either way.
Do I need party wall notices for a rear extension?
Usually, yes: for work on a shared wall, for building on the boundary, or for excavating foundations within 3 metres (or 6 metres for deeper foundations) of a neighbour's building.
How long does a single-storey extension take to build?
Typically 14 to 16 weeks on site for a single-storey rear extension in our experience, after 4 to 8 weeks of design and any time needed for planning, party wall notices and approvals.
Who books the building control inspections?
Your builder, at the stages your building control body specifies. Since October 2023 those stages are set by the building control body rather than fixed in the regulations.
When do I get the completion certificate?
After the final inspection. On the full plans route it usually arrives within eight weeks of completion. Keep it with your property documents.
Can we live in the house during an extension?
Usually, yes. Most of the work happens outside the existing house, and the most disruptive part, opening up the back wall, typically takes one to three days near the end.
Sources
- Planning Portal: householder planning consent
- GOV.UK: planning applications in England, April to June 2026
- GOV.UK: the Party Wall etc. Act 1996 explanatory booklet
- Thames Water: developing over or near sewers
- GOV.UK: building regulations approval
- legislation.gov.uk: Building Regulations 2010, regulation 16
- HSE: CDM 2015 for domestic clients
- Which? Trusted Traders: how to work with your trader
- JCT: Building Contract for a Home Owner or Occupier
This guide is general information, checked against the sources above on 3 November 2026. Every house is different, so take advice on your own property before starting work.
Planning an extension?
Get a programme and a fixed price
We visit, measure and send an itemised quote on a JCT contract, with a realistic programme for your house.